Building Timeline

  •  
    Fall 2016 (October - December)
    • User group appointed
    • RFP and review architect and CM/GC proposals
  •  
    Winter 2017 (January - March)
    • Design firm and CM/GC named and contracted
    • Conceptual building design and site visits
  •  
    Spring 2017 (April - June)
    • Conceptual building design and site layout completed for review
    • Community engagement begins
  •  
    Summer 2017 (July - September)
    • Site investigation work
    • Board of Trustees review and consideration
    • Schematic design at 50 percent
  •  
    Fall 2017 (October - December)
    • Schematic drawings finalized
    • Event for design unveiling
  •  
    Winter 2018 (January - March)
    • Schematic designs move to working drawings
    • Groundbreaking
  •  
    Spring 2018 (April - June)
    • Site work on buildings
    • Community meetings to prep for building
  •  
    Summer 2018 (July - September)
    • Building construction commences
  •  
    Fall 2018 (October - December)
    • Structural work on basement and 1st floor
  •  
    Winter 2019 (January - March)
    • Structural work on upper floors
  •  
    Spring 2019 (April - June)
    • Structural work completed
    • Glass façade of building begins
  •  
    Summer 2019 (July - September)
    • External structure of bridge complete
  •  
    Fall 2019 (October - December)
    • Glass façade of building complete
  •  
    Winter 2020 (January - March)
    • Internal finishing work underway
  •  
    Spring 2020 (April - June)
    • Commissioning of building
  •  
    Fall 2020 (September - October)
    • Opening ceremonies