Building Timeline

  •  
    Fall 2016 (October - December)
    • User group appointed
    • RFP and review architect and CM/GC proposals
  •  
    Winter 2017 (January - March)
    • Design firm and CM/GC named and contracted
    • Conceptual building design and site visits
  •  
    Spring 2017 (April - June)
    • Conceptual building design and site layout completed for review
    • Community engagement begins
  •  
    Summer 2017 (July - September)
    • Site investigation work
    • Board of Trustees review and consideration
    • Schematic design at 50 percent
  •  
    Fall 2017 (October - December)
    • Schematic drawings finalized
    • Event for design unveiling
  •  
    Winter 2018 (January - March)
    • Schematic designs move to working drawings
  •  
    Spring 2018 (April - June)
    • Site work on buildings
    • Community meetings to prep for building
  •  
    Summer 2018 (July - September)
    • Building construction commences
  •  
    Fall 2018 (October - December)
    • Construction continues
  •  
    Winter 2019 (January - March)
    • Internal work begins in building
    • Large equipment purchasing commences
  •  
    Spring 2019 (April - June)
    • Construction continues
  •  
    Summer 2019 (July - September)
    • Construction continues
  •  
    Fall 2019 (October - December)
    • Fitting out Knight Campus labs and cores
    • Soft move-in begins
  •  
    Winter 2020 (January - March)
    • Formal move-in and opening ceremony for the Knight Campus
  •  
    Spring 2020 (April - June)
    • Fitting out of internal spaces continues
    • Continue occupancy activity